SENT: June 13th, 2019 | 7:13am PDT
STATUS: At 8:12 am MDT, the Pony was reported at Ovid, Colorado, running approximately 4 hours behind schedule.

FROM: Media Team
SENT: June 13th, 2019 | 5:44am PDT
STATUS: At 6:00 am MDT the Pony was reported through Big Springs, running approximately 3.5 hrs behind schedule.

Nebraska Riders

FROM: Jack Davis
June 13th, 2019 PDT

2019 Pony Express Re-Ride Start, Patee House, St Joseph, Missouri

FROM: Dean Atkin
June 12th, 2019 PDT

FROM: Media Team
SENT: June 12th, 2019 | 10:52pm PDT
STATUS: At 12:50 am CDT, the Pony was reported at Paxton, running approximately 1 hour, 45 minutes behind schedule.

Wednesday at the Plum Creek handoff south of Overton, Nebraska.

FROM: Karen Nelson
June 12th, 2019 PDT

FROM: Media Team
SENT: June 12th, 2019 | 6:09pm PDT
STATUS: The mail arrived at North Platte about 1/2 hour behind schedule.

FROM: Media Team
SENT: June 12th, 2019 | 11:17am PDT
STATUS: At 1:15 pm CDT, the Pony was reported at Cozad, running approximately 15 minutes behind schedule.

Three Generations of Re-Riders in Nebraska

FROM: Debra S. Hill
June 12th, 2019 PDT

These were taken between The KS-NE state line and Rock Creek Station, Southwest of Fairbury NE.  Here are some pictures from the ride on Tuesday, June 11th.  These were taken by my daughter-in-law Mandi Hill.  They are: my son Richie Hill when he picks up the mochila from the Kansas riders.   Then, my grandson Blake’s first solo ride and finally grandma rides….that’s me, Debra S. Hill.

FROM: Media Team
SENT: June 12th, 2019 | 8:11am PDT
STATUS: At 9:45 am CDT, the Pony was reported at Plumb Creek, running approximately 30 minutes behind schedule.